The long awaited south hangar area reconstruction project is now complete. Work began on April 21, 2025 and was substantially complete on June 20th finishing approximately $150,000 under budget and five working days ahead of schedule.

Thanks to Cooper Engineering, McCabe Construction, and the Wisconsin Bureau of Aeronautics for their fantastic work on bringing this project over the finish line. We couldn’t be happier with the end result.